480 planned minutes
60 units/hour configured rate
420 min running60 min stopped
420 running minutes480 planned minutes
60 minutes of unplanned stops leave 420 running minutes from a 480-minute planned shift.
Availability × performance × quality. Rounded display values; OEE uses the unrounded ratios.
A working day · example scenario
The final unit count tells you what happened, but not why. Was the line stopped, running below its expected rate, or making units that could not be used? Each answer calls for a different next step.
Set the line rate and planned working minutes. A shortened shift should not be judged against a full working day.
An operator opens the line’s QR link, selects a stop reason and records the start and finish. Unplanned stops feed the availability calculation.
Review availability, performance and quality separately, then compare the leading downtime reasons. Decide which loss deserves investigation before the next shift.
A production conversation about the cause of lost output, with the underlying records to investigate it.
We put OEE alongside production records because a percentage should lead somewhere useful. Planned time, recorded stops, output and scrap provide the context for the number. A missing line rate stays undefined instead of becoming a reassuring but misleading score.
Connect the baseline to shift planning →Review availability, performance and quality separately, together with the resulting OEE.
Find the leading stop reasons. Unplanned downtime reduces availability.
Open a line-specific link on a phone, select a reason, and start or finish a stop.
Configure OEE thresholds and review daily alerts and weekly summaries.
Participating organizations can compare rounded sector aggregates when the minimum cohort is met.
Overall equipment effectiveness combines availability, performance and quality. In IEMSuite, unplanned downtime reduces availability, the configured line rate provides the performance baseline, and recorded output and scrap determine quality.
No. This workflow uses recorded production data and manual downtime entry, including the line-specific QR flow. It does not collect machine signals. OEE requires Scale; configure planned time and a line rate for meaningful results.
Use line and date filters, leading downtime causes, configured threshold alerts and weekly summaries. Anonymous sector comparisons are available only for participating organizations when the minimum cohort is met.